In a $23 million real-estate development project with a schedule of 18 months, the project plan has already been developed and approved by the stakeholders. Later, the client requests to add a change to the project without delaying the estimated due data. The client is willing to pay more for this change. What is the first thing the project manager should do?
- Start a new project for the change the client is requesting.
- Estimate contingency plans so the project is not delayed.
- Start the integrated change control process.
- Modify the scope per the client's request and send an invoice for the additional costs.