In cases where a formal contract exists between the client and the contractor, which of the following are valid procedures when dealing with changes during the project life cycle:
The changes are only issued by an authorized person.
The changes are evaluated in terms of cost, time, and performance.
The originator is made aware of the implications before the change is put into operation.