From
Project Manager: How to pass the PMP Exam without dying in the attempt:
In which project management process group are stakeholders identified?
- Controlling and Closing
- Initiating, Planning, Executing, Monitoring and Controlling
- Planning, Monitoring and Controlling
- Initiating and Planning
Remember, the PMP exam is structured as a multiple choice exam with four possible answers. Typically, two will be obviously wrong and two will be obviously correct - - only one is how the
PMI Body of Knowledge sees the world of project management.