Project Management Question of the Week

Based on the following table, what is the  critical path and what is the slack for activity A?

Activity
Duration (weeks)
Predecessor
A
10
Start
B
8
Start
C
4
A
D
7
A,B
E
10
B
F
8
C,D
G
10
D,E
H
8
F,G

Is it -
  • ADFH
  • ADGH
  • BDGH
  • BEGH
And -
  • It has no slack
  • one week
  • five weeks
  • negative one week