You are the project manager for the manufacturing of carousels for heavy products.  Last week you met with your work team to explain the requirements that need to be fulfilled in the project.  In that meeting you clarified that it is critical to not deviate from the requirements by the client.  Which quality process is this?
  • Total quality management
  • Quality assurance
  • Plan quality
  • Quality control