Project Management Question of the Week

You are the project manager for the manufacturing of a piston pump custom made for the client.  Along with the project team, you have determined what will be done when uncertain events occur and who will be the person responsible for monitoring and controlling the risks.  What has just been completed for this project?
  • Quantitative risk analysis
  • Risk responses planning
  • Risk identification
  • Qualitative risk analysis